We wanted to provide a more complete picture of what that means and why we can’t set a definitive opening date yet.

The stages to put it all together:

  1. Construction footprint – our contractor is going to put in the big footprint – removing asphalt, securing the support for the Esker and move the fences. The contractor has started mobilization which includes such things as ordering supplies, selecting boulders and stone cladding materials with our Landscape Architect, and setting up temporary construction fence.  You should begin seeing construction in action starting now (week of June 22)!
  2. Play Equipment installation – The equipment selection is still being finalized and our order should be placed the week of June 22. The installation is dependent on the equipment company’s availability and coordinating Capital One volunteers to help install (this was part of their partnership and donation commitment.) As soon as we can get a date and invite our community to help, we will. We are hoping for last week in August.
  3. Surfacing – Rubber safety surfacing under the play equipment – This order is also in progress. Once we know the delivery timeframe for the play equipment, and its installation, the company can schedule a date for installation of the safety surfacing, since the surfacing installation happens after the equipment is installed. This will hopefully happen in early September, fingers crossed!

Then, there are final inspections, and after that we can open the playground! We’ll provide updates as each key stage is completed.